Archon & Partners
☰

Guide · Getting paid

Progress billing and retainers for small architecture firms

Last updated · By Joel Angel Guadarrama

The short answer

Bill every month for the share of each phase that is done, using the fee split in your agreement, and subtract what you have already billed.

Take a retainer when the agreement is signed, hold it, and credit it on the final invoice, so the client can always see where it went.

Step by step

  1. Choose the billing method in the agreement

    Fixed fee by phase, hourly, hourly up to a cap, or a mix such as a fixed fee for design and hourly for construction administration. Write it down before work starts.

  2. Write the fee split by phase

    List each phase and the percent of the fee it carries. That table is what every progress invoice is measured against.

  3. Set the retainer terms

    State the amount, when it is due (at signing, before work starts) and how it is applied: credited on the final invoice, or against the first invoices.

  4. Fix the billing date and the route

    Invoice on the same day each month. Ask the client up front who approves invoices and what they need on them, as the AIA's Getting paid guide advises.

  5. Get percent complete from the project lead

    Each month, ask the person running the project for percent complete on each active phase. Use the deliverables list, not a feeling.

  6. Calculate this month's amount

    Earned to date is each phase's fee times its percent complete, added up. This invoice is earned to date minus everything billed before. Hourly work and reimbursable expenses go on separate lines.

  7. Show the client the math

    Put a progress table on the invoice: phase, fee, percent complete, earned, billed before, this invoice. A client who can follow the numbers has fewer reasons to hold the invoice.

  8. Apply the retainer on the final invoice

    Show the retainer as a credit line on the last invoice, with the date it was received.

Free tool

Progress billing calculator

Enter the fee, the split and how far along each phase is. It works out what to bill this month and writes the progress table for you. Nothing leaves your browser.

Phase% of fee% completeEarned
0
0
0
0
0

Replace them with your own. Percent complete is an estimate; take it from the project lead.

Four ways to bill, and what the client sees

MethodWhat you bill each monthWatch for
Fixed fee by phaseThe phase fee times its percent complete, minus what was billed beforeScope that grows inside a fixed phase
HourlyHours worked times the agreed ratesClients surprised by the total; send hours monthly
Hourly up to a capHours worked, until the cap is reachedTrack hours against the cap every month
MixedFixed phases by progress, hourly phases by hours, on one invoiceKeep the two parts on separate lines

Whatever the method, the AIA's Getting paid guide says to settle the payment route at the start: who reviews and approves the invoice, when they want to receive it, what format or information they need, and how long they take from receipt to payment.

A worked example

No currency. A fixed fee of 100,000, split 15, 20, 40, 5 and 20 percent. By the end of month four, schematic design is finished and design development is half done. Three earlier invoices total 18,000.

PhaseFee% completeEarned
Schematic design15,000100%15,000
Design development20,00050%10,000
Construction documents40,0000%0
Bidding5,0000%0
Construction administration20,0000%0

Earned to date is 25,000. Billed before is 18,000. This month's invoice is 7,000. The retainer is not touched until the final invoice.

Retainers: two ways to apply them

  • Credit on the final invoice. The retainer stays in place for the whole project, so it covers the last stretch, when unpaid work is hardest to recover. The AIA's standard owner-architect agreement (B101) has a line for an initial payment credited on the final invoice; check the wording in your edition.
  • Apply against the first invoices. Simpler for the client, but the cover is gone after a month or two.

Pick one, write it in the agreement, and repeat it on the retainer invoice. The amount is your decision; we do not suggest one.

Hourly work, additions and expenses

Keep three things off the progress table: hourly services, additional services the client approved in writing, and reimbursable expenses. Each gets its own line with its own backup (hours, the signed approval, receipts). If a request may be outside scope, use the additional services notice in the client follow-up emails guide before any work starts.

When the invoice goes out

A progress invoice still needs following up. The late invoice schedule covers the first two weeks, and the invoice chaser drafts each reminder from your own invoice list. To check that billing keeps pace with spending, compare each project's cost against its budget in the same month.

Copy-paste templates for progress billing

A retainer request, a monthly cover email, a progress table to paste into the invoice and a final-invoice note. Replace everything in [square brackets].

Download the templates as a plain text file, no signup needed.

1. Retainer request at signing

When: With the signed agreement, before work starts.

Subject: [Project]: retainer invoice to start work

Hi [first name],

Thank you for signing the agreement for [project]. Attached is the retainer invoice for [amount], as set out in [section reference].

We hold the retainer for the length of the project and credit it in full on the final invoice. Work starts on [start date] once it is received.

From [month], we will invoice on the [day] of each month for the work completed in each phase, with a table showing the progress behind each amount.

[your name]
[firm name]

2. Monthly progress invoice cover email

When: On your fixed billing day each month.

Subject: [Project]: invoice [number] for [month]

Hi [first name],

Attached is invoice [number] for [project], covering work to [date]. The amount this month is [amount], due on [due date].

The table on the invoice shows each phase, the percent complete and what was billed before, so you can see how the amount is calculated. This month we [one line on progress, for example completed design development and started construction documents].

If anything on it needs explaining, reply here or call me on [your number].

[your name]
[firm name]

3. Progress table for the invoice

When: Paste into the invoice body or attach it. The calculator above fills it in for you.

Subject: Progress to [date]

Phase | Fee | % complete | Earned to date | Billed before | This invoice
[Schematic design] | [fee] | [%] | [earned] | [billed] | [amount]
[Design development] | [fee] | [%] | [earned] | [billed] | [amount]
[Construction documents] | [fee] | [%] | [earned] | [billed] | [amount]
[Construction administration] | [fee] | [%] | [earned] | [billed] | [amount]
Total | [total fee] | [overall %] | [earned] | [billed] | [amount]

Hourly services this period: [hours and amount, or none]
Reimbursable expenses this period: [amount, receipts attached]
Retainer held: [amount], credited on the final invoice

4. Final invoice with the retainer credit

When: With the last invoice on the project.

Subject: [Project]: final invoice [number]

Hi [first name],

Attached is the final invoice for [project]. It bills the remaining [amount] of the fee and credits the retainer of [retainer amount] received on [date], as set out in [section reference]. The balance due is [balance], by [due date].

Thank you for the work together on [project].

[your name]
[firm name]

Frequently asked questions

What is a retainer for an architect?

Money the client pays when the agreement is signed, before work starts. The firm holds it and usually credits it on the final invoice. It shows commitment and covers part of the risk of unpaid work. Ask your accountant how to record it: until it is applied, it is money received in advance, not income.

Should a small firm bill monthly or at the end of each phase?

Monthly. Emily Rae of Fletcher Priest Architects warned in the RIBA Journal against tying payments to the completion of work stages, which can mean months without payment. Monthly progress billing keeps cash coming in while a long phase runs.

Isn't percent complete just a guess?

It is an estimate, which is why it should come from the project lead and be tied to deliverables. List the sheets or tasks in the phase and count what is done. If the client asks, you can show the list.

Where does the fee split by phase come from?

From your agreement. Many US firms start from a split close to 15, 20, 40, 5 and 20 percent across schematic design, design development, construction documents, bidding and construction administration. That is a convention, not a standard. Adjust it to how the work on each project really falls.

What if the client disputes the percent complete?

Walk them through the deliverables behind the number. If you agree a lower figure, bill that and catch up next month; the total fee does not change, only the timing.

Sources

Book your free Admin Map.